This guide covers upgrading a running Dependency-Track cluster to a new version with no planned downtime. For breaking changes between specific releases, always consult the per-release upgrade guides before starting.

When you can upgrade in place

The durable execution engine, leader election, and lock-free task claiming make it safe to replace one API server instance at a time as long as:

  • The release notes describe no breaking schema changes that require all instances to stop.
  • The destination version's Liquibase migrations are additive against the running schema.
  • More than one instance is running. A single-instance deployment cannot upgrade without downtime.

If any of these conditions fail, plan a full-stop upgrade window instead.

Before you start

  • Back up the database and verify the backup. See Backing up.
  • Read the release notes for every version between the running and target version. Stop and plan a full-stop upgrade if any release calls for one.
  • If you run schema migrations in a dedicated container (recommended for large deployments and PgBouncer in transaction mode), plan to run it before any new-version API server starts. See Schema migration credentials.

Rolling upgrade

  1. Run schema migrations, either via the dedicated container or by letting the first new-version instance run them on startup.
  2. Replace API server instances one at a time using your platform's rolling-update primitive. Background tasks claimed by an instance that stops mid-flight return to the queue when the database transaction ends; another instance picks them up on its next poll.

Old and new instances run side by side until the roll-out completes. The "additive migrations" condition listed earlier is what makes that safe: the old version must keep working against the migrated schema for the duration of the roll-out. Cap the roll-out to a single deploy window. Do not leave the cluster running mixed versions indefinitely.

If a migration fails partway and leaves the Liquibase change-log lock held, clear the lock in PostgreSQL before retrying the upgrade.

Web/worker split

When the cluster splits API and worker traffic, upgrade both groups using the same one-at-a-time pattern. Upgrade workers first so the API tier always talks to a database whose schema the workers already understand.

When to fall back to a full-stop upgrade

Plan a full-stop maintenance window when:

  • The release notes call for one explicitly.
  • The migration involves long-running data back-fills or partition rewrites.
  • You cannot guarantee at least one instance remains running throughout.